Specialists of the Labinsky branch of Rosseti Kuban met with the children spending a vacation in the summer camp "Little Country" on the basis of school No. 1 in Labinsk, and told them about the rules of electric safety on the street and in everyday life.
Specialists of the Adygei branch of Rosseti Kuban carried out major repairs of sites of two 110 kV overhead power lines (OHPL) Central - Cheremushki and Cheremushki - Hadzhokh. Energy facilities provide electricity to the city of Maykop and the Maykop district of the Republic of Adygea with a total population of about 200 thousand people.
Specialists of the Ust-Labinsk branch of Rosseti Kuban continue to repair the 110 kV Novolabinskaya-Korenovskaya-Tyagovaya high-voltage overhead power transmission line (OPTL) with a length of about 40 km. This will improve the reliability of power supply to the Korenovsky and Ust-Labinsky districts of the Krasnodar Territory.
Specialists of the Krasnodar branch of Rosseti Kuban started the reconstruction of the 35 kV substations Dinskaya and Staromyshastovskaya in the Dinskoy district of the Krasnodar Territory. The company plans to allocate more than 74 million rubles for the repair of these power centers.
In 2022, Ust-Labinsk branch of Rosseti Kuban has consolidated 56 unpossessed power facilities in Vyselkovsky, Korenovsky, Tbilissky and Ust-Labinsky districts of the Krasnodar Territory. Among the assets accepted on the account there are 48 transformer substations and eight 10-0.4 kV power transmission lines with a total length of 6 km.
Within the framework of modernization of the power grid infrastructure in Yuzhny settlement in the suburbs of Krasnodar, where there is an increase in energy consumption due to active housing development, Rosseti Kuban specialists have built new and reconstructed existing power transmission lines (PTL) and transformer substations.
A meeting on electric grid complex development in Krasnodar Territory and the Republic of Adygei was held in the Executive office of Rosseti Kuban, and all the branches of the company have obtained certificates of readiness for the autumn-winter period of 2022/2023 within the framework of it.
Since the beginning of 2022, the power engineers of Sochi branch of Rosseti Kuban have made technological connection of three new healthcare institutions in settlements of the Sochi electric power area. The total power provided to primary medical assistance objects by the company has exceeded 100 kW.
The final assessment on the program ‘A training school for specialists on development and implementation of services’ was held at the Corporate Power Engineering Institute for Advanced Training. This year nine employees of ‘Rosseti Kuban’ have become graduates of this professional retraining course.
Following the results of ten months, specialists of Labinsk branch of ‘Rosseti Kuban’ identified about 80 cases of non-contractual and unaccounted electrical power consumption in Labinsky, Kurganinsky and Mostovsky Districts of Krasnodar Krai. The total amount of illegally consumed electrical power was about 1.5 million kW*h according to the revealed facts.