Rosseti Kuban prepared Shovgenovskaya substation in Adygea for the autumn-winter period
Back

In the Adygea branch of the Rosseti Kuban company, power engineers completed the repair of the equipment of the 110 kV Shovgenovskaya substation. The high-voltage supply center provides electricity to more than 16 thousand people and socially significant facilities in eight rural settlements of the Shovgenovsky district of the Republic of Adygea.

The specialists of the power company repaired switches, transformers, disconnectors, switchgears at the substation, and also performed a set of fire prevention measures, updated dispatching names.

It will be recalled that earlier in the Shovgenovsky district of the Republic of Adygea, power engineers began repairing the equipment of the 35 kV Chernyshevskaya substation. The power supply of about 2.5 thousand people and socially significant objects in the farms Chernyshev, Vesely, village Ulsky and aul Pshizov depends on the reliability of the high-voltage main substation.

Adygea electric networks provide electricity to eight municipalities: Maykop, Giaginsky, Shovgenovsky, Koshekhablsky, Krasnogvardeisky districts and the city of Maykop of the Republic of Adygea, as well as the Absheron and Belorechensky districts of the Krasnodar Territory with a total population of about 550 thousand people. In the area of responsibility of the branch – 59 substations of 35-110 kV and 2,212 transformer substations. The total installed capacity is 1,150 MVA.