On October 10 in the afternoon dispatcher office of Vyselkovskiy district received an alarm on emergency shutdown of transformer substations in Inogorodne-Malyovanniy settlement. The cause of the accident was the car crashed into 6kV overhead transmission tower.
Commission for checking the preparedness of Kubanenergo branches to autumn-winter season 2012-2013, consisting of technical inspection, production control inspection and occupational safety specialists from Kubanenergo and Federal Service for Environmental, Technological and Nuclear Supervision, confirmed the readiness of Kubanenergo branch Tikhoretskiye electric grids to autumn-winter peak loads.
Under the Programme of reparation to autumn-winter season specialists of Kubanenergo (part of Russian Grids JSC) overhauled more than 93 km and checked more than 1530 km of overhead lines in Slavyanskiy, Krasnoarmeiskiy and Temtyukskiy districts of Krasnodar region.
Specialists of Kubanenergo (part of Russian grids group) perform maintenance works on equipment of five substations of 35-110kV that feed about 20 thousand consumers and 47 facilities of social importance in six settlement of Kurganinskiy and Labinskiy districts of Krasnodar region.
Specialists of Kubanenergo (part of Russian grids group) install for consumers involved in resort business and consumers included in “risk group” the Automatic systems for commercial accounting of power consumption (ASCAPC) in Golubitskaya village of Temryukskiy district, Krasnodar region.
Kubanenergo JSC (part of Russian grids group) completed overhaul of 23 overhead lines at Black seas coast – in Anapa, Gelendzhik, Novorossiysk, Krymskiy and Abinskiy districts.
Under the programme of predation to autumn-winter season 2013-2014 specialists of Kubanenergo (part of Russian grids group) have repaired 35kV substation Shkolnaya in Anapa, Krasnodar region.
The programme of Kubanenergo (part of Russian Grids JSC) on preparation to autumn-winter season 2013-2014 included tests on systems of de-icing 110kV HV lines “Tikhoretsk - Rassvet” of 34.2 km and “Kropotkin-Tbilisskaya” of 29.4 km.
Kubanenergo JSC initiated in Yeiskiy, Leningradskiy, Kuschyovskiy and Scherbinovskiy districts of Krasnodar region meetings with heads of large enterprises and organizations which power receivers’ is 670kW and more.
Kubanenergo (part of Russian Grids Group) actively improves quality of energy supply in Adlersky city district of Sochi. The major work on installation of cable lines is accomplished, 10 new package transformer substations are installed.