Rosseti Kuban completed the reconstruction of a large substation in the Kanevsky district
Back

Specialists of the Timashevsky branch of Rosseti Kuban completed the reconstruction of the substation Kanevskaya with a voltage level of 35 kV with an increase in its capacity by 1.6 times in the village of the same name in the Krasnodar Territory. The energy company allocated more than 45 million rubles for the project.

The 35 kV substation Kanevskaya is one of the key feeding centers of the village of Kanevskaya. It provides electricity to more than 23 thousand subscribers and 13 socially significant facilities: educational and health care institutions, treatment facilities, artesian wells and others.

During the reconstruction of the power substation, the power transformer was replaced, increasing the total power of the feeding center from 16.3 MVA to 20 MVA. This will ensure reliable electricity supply to consumers and meet the growing energy needs of the agricultural and industrial facilities of the village.

– The reconstruction of the feeding center was carried out using modern equipment of domestic production", said Sergey Sobolev, director of the Timashevsky branch of Rosseti Kuban. – As a result of the works performed, the substation capacity was increased by 1.6 times. This will significantly increase the reliability of power supply to consumers connected to the feeding center.