Rosseti Kuban plans to invest 8 billion rubles in renovation of energy complex of the region
Back

In 2021, the number of investments of Rosseti Kuban in modernization and construction of new integrated power grid facilities of Krasnodar Region and the Republic of Adygeya will amount to about 8 billion rubles. The energy company plans to allocate 6,058 billion rubles, as well as 1,875 billion rubles in the Republic of Adygeya, for investment projects.

According to the results of 2020, the amount of financing of the Company’s investment programme amounted to 5,626 billion rubles. Thus, the investment increment aimed at construction and reconstruction of power facilities of Kuban and the Republic of Adygeya amounted to about 40 percent in the current year.

In Krasnodar and a suburb of the capital of the region, reconstruction of substation “Starokorsunskaya” with a voltage of 110 kV, and construction of new high voltage lines are planned. At present, one of the most important power facilities of the city is being modernized - substation 110 kV “Pochtovaya”. The supply centre capacity which provides power supply to citizens of the Hidrostroiteley micro-district, will be increased by a third after modernization and will amount to 80 MVA.

In the Sochi energy area, substations 110 kV “Pasechnaya”, “Adler”, and “Kudepsta” will be modernized. In total, their capacity will be increased by 96 MVA.

In 2021, the large-scale reconstruction with the increase in the capacity of substations 110 kV “Adygeyskaya” and 35 kV “Kuzhorskaya” is planned in the Republic of Adygeya.

PJSC Rosseti Kuban is in charge of the electric power transmission through the networks with a voltage of 110 kV and lower in the territory of Krasnodar Region and the Republic of Adygeya. There are eleven electric grid branch offices as a part of power grid. The total length of transmission lines is up to 93 thousand km. The square of service area is 83,8 thousand sq km with population more than six million people.