Ust-Labinsk branch to invest 76 million rubles in power lines repair project
Back

As part of the Repair Programme 2019, 825 km of overhead power lines of the distribution network of four districts of Krasnodar region will be modernized by Ust-Labink electric networks, branch of Kubanenergo PJSC  (Rosseti Group).

Repair of 0.4-10 kV overhead lines will be carried out in Vyselkovsky, Korenovsky, Tbilissky and Ust-Labinsk districts, which are in the area of responsibility of the branch. Our specialists will use self-supporting insulated wire, which, compared to traditional non-insulated wire, has higher level of electrical safety; it is also more resistant to icing and damages caused by falling trees.

Mikhail Suvorov, Director of Ust-Labinsk electric networks, said: “The necessity of scheduled maintenance is caused by physical deterioration of power equipment. As part of the repair programme, the branch will invest 76 million rubles in the distribution network. Currently we are planning to ensure the reliability of power supply to consumers by introducing modern technologies.”

To prevent technological disruptions and ensure more reliable and high-quality power supply to consumers, Ust-Labinsk electric networks annually implements a large-scale repair programme. Some types of work require temporarily limiting of supply in order to replace equipment. Regional and municipal authorities, and Unified Dispatch Services will be notified about power cutoffs in advance, the latter will inform customers.