170 million rubles on power upgrade project in Timashevsky district
Back

Timashevsk branch of Kubanenergo PJSC  (Rosseti Group) invested over 170 million rubles in construction and modernization of grid facilities in its area of responsibility in 2018.

Throughout 2018, engineers constructed and put into service 35 transformers of total capacity of 4.6MVA and 23km of 10/0.4kV overhead power lines in Timashevsk, Kalininsky, Kanevsky, Bryukhovetsky, and Promorsko-Akhtarsk districts of the Krasnodar region.

Two high-voltage substations were upgraded by installing modern equipment and applying technical innovations. In particular, our construction teams repaired and upgraded switchboard at substation “Novodzherelievskaya” and installed modern protection against short circuits; they also installed innovative microprocessor-based protection at substation “Kalininskaya”.

As part of reconstruction of railway lines of Krasnodar hub of the North-Caucasian Railway, our engineers moved 10, 35, and 110kV power lines.

Implementation of the Investment Programme of Kubanenergo will help increase reliability of equipment and ensure a secure and reliable supply of power to properties, businesses and vital infrastructure of the Krasnodar region.