Within the framework of the Repair Programme 2018, specialists from of the Adygea branch of Kubanenergo PJSC (Rosseti Group) have completed repairs of the equipment of 35 kV “Guzeriple” substation in Maykop district of Adygea. The total cost of the project was about 800 thousand rubles.
This substation is one of the key facilities of the power system of the mountain area of the republic, providing electricity to the consumers of the village Guzeripl.
To ensure uninterrupted operation of the power substation, our specialists repaired oil switches, disconnectors, drives and bus bar systems; carried out preventive works using telemechanics and communication equipment. Timely and qualitative performance of repair works helps maintain equipment at the appropriate level.
Yury Khomichenko, director of the Adygea power networsk, said: “ Preparation for this autumn-winter period is one of the most important activities of the company. During this period, the power grid is being prepared for operation during unstable weather conditions and low temperatures in order to provide reliable power supply to customers and in Krasnodar region and Adygea, as well as to reduce power losses in the networks.” |