Specialists from South-Western branch of Kubanenergo PJSC (Rosseti group) have started on essential project to repair equipment of 110 kV substation ‘Tonelnaya’. This high-voltage substation keeps lights on for more than 10 thousand homes and dozens of public amenities at the suburbs of Novorossiysk.

Our engineers will repair switches, disconnectors, switchgear devices of the substation and clean the equipment. Power engineers will replace obsolete substation equipment with a more modern one, refresh paint on structures, update dispatcher names and safety signs, and install fencing.

‘Our task is to perform timely this repair project, thereby ensure stable and high-quality power supply for our consumers. Overhaul of the substation is carried out within the Kubanenergo’s Repair Programme 2018. The total cost of repair project will be about 1.7 million rubles,’ said Dmitry Golovakha, the director of the South-Western branch of Kubanenergo.