Specialists of Adygeiskiye electric networks, Kubanenergo PJSC (Rosseti group), have finished repair of equipment at 35kV substation “Pshekhskaya” in Belorechenskiy district, Krasnodar region.
To increase the reliability of power facility, engineers carried out maintenance and repair work at 48 units of substation equipment. The power project included repair of switchers, voltage transformers, details of spark gaps, inputs, busbar disconnectors and overvoltage limiters.
“Pshekhskaya” substation supplies with electric energy several settlements in Belorechenskiy district, soft infrastructure and big industrial enterprises.
‘This project is part of Repair Programme 2018, the goal of which is stable operation of power grid in autumn and winter period. In the nearest time we will start repairing 35kV substation “Ryazanskaya-2” to increase quality and reliability of power supply to six thousand customers in several settlements of Belorechenskiy district,’ said Yuri Khomichenko, director of Adygea branch of Kubanenergo PJSC. |