58-million-ruble investment set for Tikhoretsk power network
Back

In 2018 Kubanenergo PJSC  (Rosseti Group) plans to invest over 58 million rubles in repair of power equipment in five districts of the Krasnodar region that are serviced by Tikhoretsk branch.

Repair of equipment will be carried out at 19 high-voltage substations. Our engineers also plan to perform major repairs of 16 high-voltage power lines and 47 lines of the distribution network.

In total, the project will replace 44 transformers, about 500 poles, over 4.1 thousand old insulators with the modern glass ones, 94 km of bare wire and 12 km of lightning protection cable. To prevent power disturbance caused by trees falling on wires, it is planned to clear 90 hectares of power transmission lines using special equipment – a mulcher. A great amount of work will be done by the Company itself – without using services of contractors.

“Repair the main and auxiliary equipment of substations and transmission lines are conducted annually, with the approved regularity and strictly according to plan. We strive to constantly improve the quality and reliability of power supply for large enterprises, social facilities and household consumers in rural settlements,” said Valery Gondar, the director of Tikhoretsk branch of Kubanenergo.