Employees of Labinskiy branch of Kubanenergo PJSC (Rosseti group) are finishing the repair of 35 kV “Chamlyk” and “Temirgoevskaya” substations to get them ready for autumn and winter period. These power centres keep lights on for four settlements in Labinskiy and Kurganinskiy districts.
Engineers have repaired and tested equipment of substations: power transformers, oil circuit breakers, disconnecting switches, busbar sections and other equipment. And now they are repairing substation integration modules. Besides that, they will clear the territory of power facilities from dead vegetation, replace gravel near power transformers and restore safety signs to comply with fire prevention rules.
High-voltage substations “Temirgoevskaya” and “Chamlyk” are the main sources of power supply to residential and industrial consumers, and public facilities of Temirgoevskaya, Chamlykskaya, Novolabinskiy and Laboda villages.
– The completed works are aimed to increase the lifetime of power equipment and provide qualitative and uninterrupted power supply to customers in two villages of Labinskiy power district, - said Andrei Gerasko, director of Labinskiy branch of Kubanenergo.