To prepare the equipment to summer peak loads, power engineers of South-Western branch of Kubanenergo PJSC (Rosseti group) conducted thermovision inspection of 20 high voltage power lines of total length 277 km in Anapa, Gelendzhik, Novorossiysk and Krymsky districts of Krasnodar region.
These high voltage power lines provide more than 260 thousand residential customers, about 760 social facilities and six big recreation centres on the Black sea coast of Krasnodar region.
Practice of using thermovision inspection of Kubanenergo equipment allows to draw an accurate conclusion on condition of object, reduce an amount of repair works, increase safety of power equipment operation and provide the reliability of power supply of customers.