Engineers of Kubanenergo repaired high-voltage power line in Ust-Labinsk district
Back

Engineers of Ust-Labinsk branch of Kubanenergo PJSC (Rosseti group) carried out of repairing works on the 110 kV “Ust-Labinskaya tyagovaya – Ladozhskaya” power line in Ust-Labinsk district, Krasnodar region.

Our teams have replaced 21 sets of overhead line accessories, 83 default insulators, renewed enumeration, run diagnostics of metal poles and foundations, performed measurements of grounding contour on the poles. They have also trimmed trees and vegetation near the lines.

“Ust-Labinskaya tyagovaya – Ladozhskaya” power line is involved in power supply of 17 000 citizens and 10 important infrastructures of two settlements in Ust-Labinsk district.

Mikhail Suvorov, director of Ust-Labinskiye electric networks, said: “Repair works that were performed by our specialists, allow to decrease the possibility of technological disturbances and to provide efficient and reliable power supply especially during unfavorable weather conditions and peak demand.”.

The repair programme 2017 in Ust-Labinsk power district includes the repair of 7 high-voltage substations and 47 low-voltage transformer substations. Total length of 35-110 kV power lines that were included in repair programme 2017, amounts 82 km.