Kubanenergo started overhaul of substation “Sergievskaya” in Korenovskiy district
Back

Engineers of Ust-Labinskiy branch of Kubanenergo PJSC (Rosseti group) commenced overhaul of 35kV substation “Sergievskaya”. The project will repair substation equipment and will end in several months.

Our teams will repair oil switches and 35 kV disconnectors, static condenser unit and 10kV switchgear, they will also conduct diagnostic of relay protection and automation devices, transformer cooling and heating systems, mechanical interlocks, paint metal structures and and carry out land improvements.

Mikhail Suvorov, director Ust-Labinskiy branch, said: “This overhaul will help protect equipment, prevent technological faults and ensure uninterrupted power supply to industries, businesses, agricultural enterprises and individual customers.”

Substation “Sergievskaya” keeps the lights on for three thousand customers in Sergievskaya village, as well as socially significant facilities, such as schools, nursery schools, medical and obstetrical station, two boiler plants and pumping station.