90% of substations in Krasnodar district are ready for winter season
Back

Maintenance crews of Krasnodar branch of Kubanenergo PJSC (Rosseti Group) have prepared over 90% of substations for winter. These substations supply electricity to more than 200 thousand customers in suburbs of Krasnodar, Dinskoy, Severskiy and Goryacheklyuchevskoy districts of the Krasnodar region and Teuchezhskiy and Takhtamukaiskiy districts of the Republic of Adygea.
The planned programme of maintenance for 2016 includes repair of 12 substations of 35 and 110kV. Our teams have already repaired 11 substations.
At each substation we repaired main and auxiliary equipment, adjusted protection and automation systems, diagnosed and tested oil-filled equipment.
Vladimir Mikhailov, head of Krasnodar electric networks, Kubanenergo PJSC, said: “Such multi-pronged approach helps carry out repair and maintenance of all equipment, which will ensure high operation efficiency now and for years to come and greatly increase safety of substation personnel.”
The programme of maintenance started in March and is due to finish in October. Then a specially established committee will check the readiness of the power network to autumn-winter season.