Branch of Kubanenergo PJSC (Rosseti Group) - Ust-Labiniskiye electric networks carry out maintenance at “Bezlesnaya” substation in Ust-Labinsk district.
At 35/10KV substation our teams carry out repair and maintenance work; they have repaired disconnectors and short-circuiting switches of transformers, carried out maintenance of section oil circuit breaker and oil circuit breakers of 35kV. The exterior of substation was completely renovated.
Alexandr Kolodkin, head of group of subsations, said: We strive to complete repair works in the shortest possible tim as it helps reduce the period of cutting off electricity for consumers and socially important facilities”. |
35/10KV substation “Bezlesnaya” was commissioned way back in 1972. It is of vital importance for one of the largest agricultural facilities of the district – “Experimental Production Farm named after Timiryazev K.A.” that includes “Scientific research centre and development in the field of natural and technical sciences”.