65 power grid facilities were constructed and reconstructed in Temryuk district for customers of preferential category
Back

As part of investment programme the employees of Slavyansk branch of “Kubanenergo” PJSC (“Rosseti” group) from the beginning of 2016 have constructed and reconstructed 65 power grid facilities for customers of preferential category in Temryuk district of the Krasnodar region.
The length of constructed and reconstructed power lines of 0.4-10 kV distribution grid reached 11 kilometers. Employees constructed and upgraded several package transformer substations with increasing of transformer capacity.
Implemented measures allowed to provide technical capabilities for connection of more than 70 new customers of preferential category to electric networks in 30 settlements of Temryuk district. Besides the implemented works allowed to increase the reliability and quality of electric energy supply to customers that were connected to electric networks of branch earlier.
The following customers are referred to preferential category: customers that consume up to 15 kW inclusive, on condition that the distance from applicant to facilities of grid complex does not exceed 300 meters in urban settlements and 500 meters in rural settlements. In spite of implementation of the set of works necessary for connection, its cost for customers of preferential category remains the same – 550 rubles.