Kubanenergo constructed and reconstructed more than 150 km of power lines in Slavyanskiy power district
Back

From the beginning of 2015 the specialists of Slavyanskiy branch of “Kubanenergo” PJSC (“Rosseti” group) have constructed and reconstructed more than 150 km of 0.4-10 kV overhead power lines as part of investment programme for customers as beneficiary consumers in Slavyansk, Krasnoarmeisk and Temryuk districts of Krasnodar region.

As part of investment programme they also constructed 3 new transformer substations, replaced with increase in and installed 83 power transformers. Total capacity of power facilities of distribution network that were put into operation from the beginning of 2015 exceeded 33 MVA.

These actions allowed to create technical capabilities for connection to power network of more than 1000 new consumers of privileged category in Slavyansk, Krasnoarmeisk and Temryuk districts of Krasnodar region.

The implemented works increased the reliability and quality of customers’ power supply connected earlier to networks of branch.

To the beneficiary category are referred those customers that consume less than 15 kW, and with distance from borders of land plot to electric network of required voltage class less than 500 meters for villagers and 300 meters for urban residents. Price of the work on connection is still 550 rubles.