30km power line “Malokubanskaya - Ploskaya” repaired in Novopokrovsky district
Back

Within the framework of implementation of the repair programme and in order to prepare grid facilities for winter, the specialists of Kubanenergo PJSC (Rosseti group) have accomplished overhaul of 32 km overhead power line “Malokubanskaya - Ploskaya”. The implemented activities made possible to enhance reliability of power supply for six thousand residents in Novopokrovsky district.

Power engineers of Tikhoretskiye electric networks, branch of Kubanenergo PJSC, repaired ten reinforced concrete poles and four transmission-tower footings, removed 270 worn out insulators and installed modern ones made of tempered glass instead. Such types of glasses have greater insulating capability, mechanical performance; they are more resistant to temperature drop and environmental load.

Our teams also cut and trimmed trees and vegetation near electricity lines. The Company did not attract any third party organizations for repair of high-voltage equipment, performing all the works using its own resources.

High-voltage line “Malokubanskaya - Ploskaya” provides electricity to over six thousand customers and several socially significant facilities in Pervomaisky, Oktyabrsky, Gorkaya Balka, Khleborob and Noviy Mir villages, partially to Novoivanovskaya and Ploskaya villages of Novopokrovsky district, Krasnodar region.

This set of activities implemented by power engineers in accordance with repair programme will ensure safe and reliable power supply to homes and businesses during the upcoming autumn-winter season.