Kubanenergo plans to carry out 80% of repair works in Armavirsky district using its own resources in order to enhance efficiency and reduce operating costs.
Under repair programme 2015 a preparation of equipment to autumn-winter season has started in Armavirsky branch of Kubanenergo JSC. The responsibility area of the branch includes suburbs of Armavir, Novokubansky, Uspensky, Otradnensky, Gulkevichesky and Caucasian distracts of Krasnodar region.
During 2015 engineers of Armavirskiye electrical networks will repair 9 substations of 35-110kV, overhaul 500 km of overhead lines of various voltage, clear from trees and brushes about 30 hectares of line routes. They also plan to replace more than 350.
Increase of works performed using its own resources helps reduce the costs and does not require tender procedures for selection of a contractor.