Labinskiy branch of Kubanenergo JSC (part of Russian Grids group) made a schedule of repairs of main and auxiliary equipment in 2014. Specialists will repair and service 42 substations and 16 overhead power lines in Kurganinskiy, Labinskiy and Mostovskoy districts of Krasnodar region.
The following substations will be overhauled: 110/35/10kV “Andreyedmirtievskaya” substation and seven substations of 35/10kV – “”Akhmetovskaya”, “Kaladzhinskaya”, “Mikhailovskaya”, “Vostochnaya”, “Sadovaya” and “Pervaya Sinykha”. These substations provide energy supply to 20 thousand consumers and 50 socially important buildings in 22 settlements of Kurganinskiy, Labinskiy and Mostovskoy districts. Apart from it, 34 substations of 35/110kV will be also repaired and serviced.
It is also planned to repair 16 overhead lines of 35-110kV of total length more than 12 km. About one thousand insulators and 13 transmission towers will be replaced, and 17 hectares of line routes will be cleaned from bushes and trees.
This set of activities planned as part of repair programme for 2014 is to improve quality and enhance reliability of energy supply to household users, large industrial and agriculture companies and utility facilities in Kurganinskiy, Labinskiy and Mostovskoy districts of Krasnodar region.