Specialists of Kubanenergo (part of Russian grids group) perform maintenance works on equipment of five substations of 35-110kV that feed about 20 thousand consumers and 47 facilities of social importance in six settlement of Kurganinskiy and Labinskiy districts of Krasnodar region.
Labinskiye electric grids have accomplished maintenance works at 2.5MVA power transformer and other equipment of 110kV substation “Kompleks”. The substation serves for more than 20 thousand consumers in Svetlaya Zarya and Svoboda villages, 14 socially important facilities such large enterprise in Kurganinskiy district – “Kurganinskiy poultry plant”.
By the end of August specialists of the branch plan to troubleshoot the equipment of four substations of 35kV: “Vladimirskaya”, “Sadovaya”, “Poliv” and “Temirgoyevskaya”. These facilities supply about 18 thousand consumers from Labinskiy districts of Krasnodar region.
Well-timed implementation of maintenance works and technical servicing of equipment under the programme of preparation of Kuban to autumn-winter season, are to prevent accidents and provide domestic and industrial consumers, public facilities with reliable and uninterrupted power supply.