Kubanenergo prepares distribution grid of Black seas coast to autumn-winter season
Back

Kubanenergo JSC (part of Russian grids group) completed overhaul of 23 overhead lines at Black seas coast – in Anapa, Gelendzhik, Novorossiysk, Krymskiy and Abinskiy districts. 

 

Under the repair programme 2013 specialists of Kubanenergo branch South-Western electric grids have repaired 10 power lines of 6-10kV and 12 power lines of 0.4kV. Total length of repaired lines is 70km. 

 

Our specialists also replaced 9 overloaded transformers for a larger capacity, 27 transformers were repaired, more than 30 km of bare conductor and 1200 insulators were replaced. 

 

For increasing reliability of operation of electric grid complex South-Western branch cleared from bushes and trimmed trees of 30 hectares area of 0.4/6kV power line routes. 

 

Also as a part of preparation to autumn-winter season the company checks completeness with special clothes, readiness of vehicles.